L and M together can complete a piece of work in 72 days, M and N together can complete it in 120 days, and L and N together in 90 days. In what time can L alone complete the work?
Let L does a units of work/day
M does b units of work/ day
N does c units of work/ day
Now as per given conditions :
Let work be W
So we get
W = 72(a+b) =120(b+c) =90(a+c)
we get
6a+6b = 10b +10c
we get 6a-4b-10c=0 (1)
also
4a+4b =5a+5c
we get a-4b+5c =0 (2)
From (1) and (2)
we get a=3 , b=2 and c=1
Now therefore W = 360
Now time taken by L alone to complete the work = 360/3 = 120 days
Click on the Email ☝️ to Watch the Video Solution
Create a FREE account and get:
Book Free CAT Mentorship
Get personalized CAT strategy from a 99%iler
500+ students mentored
OTP Verification
Enter the 6-digit code sent to your phone
Booking Summary
Enter OTP
Didn't receive the OTP?
Start your IIM journey with the right preparation and crack CAT 2026.
Educational materials for CAT preparation