Teams A, B, and C consist of five, eight, and ten members, respectively, such that every member within a team is equally productive. Working separately, teams A, B, and C can complete a certain job in 40 hours, 50 hours, and 4 hours, respectively. Two members from team A, three members from team B, and one member from team C together start the job, and the member from team C leaves after 23 hours. The number of additional member(s) from team B, that would be required to replace the member from team C, to finish the job in the next one hour, is
CAT Time and Work Questions
CAT Time and Work Questions
Let the per hour productivity of each member from teams A, B, and C, be $$a$$, $$b$$, and $$c$$ units respectively.
Let $$W$$ be the total units of work that each of the teams does. We have:
$$W = 40*5*a = 50*8*b = 4*10*c$$
This gives, $$a= \dfrac{W}{200}$$, $$b= \dfrac{W}{400}$$, and $$c = \dfrac{W}{40}$$
When two members from team A, three members from team B, and one member from team C together start the job, the total per hour productivity for the first 23 hours will be;
$$\dfrac{2W}{200} + \dfrac{3W}{400} + \dfrac{W}{40} = \dfrac{17W}{400}$$.
In 23 hours, the work done will be $$\dfrac{23*17W}{400} = \dfrac{391W}{400}$$
The remaining work, after 23 hours, is $$W - \dfrac{391W}{400} = \dfrac{9}{400}$$
The current per hour efficiency of the group that comprises members from only teams A and B, is $$\dfrac{2W}{200} + \dfrac{3W}{400} = \dfrac{7W}{400}$$
In the next hour, the members from A and B will finish $$\dfrac{7W}{400}$$ units of work and $$\dfrac{9W}{400}-\dfrac{7W}{400} = \dfrac{2W}{400}$$ units of work would remain.
This work has to be finished by newly added members from team B in one hour, therefore, the number of new members required from team B would be $$\dfrac{2W}{400} \div \dfrac{W}{400} = 2$$
Option B is the correct answer.
The rate of water flow through three pipes A, B and C are in the ratio 4 : 9 : 36. An empty tank can be filled up completely by pipe A in 15 hours. If all the three pipes are used simultaneously to fill up this empty tank, the time, in minutes, required to fill up the entire tank completely is nearest to
Let the rate of flow of water from pipe A be $$4x$$ units per hour. From the ratio of the rates of flow of water (4:9:36), we have that the rate of flow of water from pipe B should be $$9x$$ units per hour, and from pipe C should be $$36x$$ units per hour.
Since pipe A fills the empty tank in 15 hours, the capacity of the tank must be $$15\times 4x = 60x$$ units.
When all three pipes work together, their combined capacity would be $$4x+9x+36x = 49x$$ units per hour.
Therefore, the time it would take for the three pipes to fill the empty tank working together is: $$\dfrac{60x}{49x}$$ hours
In minutes, this time is equivalent to $$\dfrac{60x}{49x}\times 60 \approx 73.47$$ minutes.
Option A is the closest, and is the correct answer.
Arun, Varun and Tarun, if working alone, can complete a task in 24, 21, and 15 days, respectively. They charge Rs 2160, Rs 2400, and Rs 2160 per day, respectively, even if they are employed for a partial day. On any given day, any of the workers may or may not be employed to work. If the task needs to be completed in 10 days or less, then the minimum possible amount, in rupees, required to be paid for the entire task is
Let's assume that Total work = 1
If the work is entirely carried by each one of them it would cost
Arun: $$2160 \times 24 = 51840$$
Varun: $$2400 \times 21 = 50400$$
Tarun: $$2160 \times 15 = 32400$$
The cheapest worker is Tarun. He can finish the work in 15 days. But we need the work completed in 10 days.
Tarun does $$10 \times \dfrac{1}{15} = \dfrac{2}{3}$$
$$1 - \dfrac{2}{3} = \dfrac{1}{3}$$
Complete the remaining (1/3) work using the next cheapest worker, which is Varun.
Days needed: $$\dfrac{x}{21} = \dfrac{1}{3} \quad\Rightarrow\quad x = 7$$
Total cost = Amount paid for Tarun + Amount paid for Varun = $$10 \times 2160 + 7 \times 2400 = 38400$$
Ankita is twice as efficient as Bipin, while Bipin is twice as efficient as Chandan. All three of them start together on a job, and Bipin leaves the job after 20 days. If the job got completed in 60 days, the number of days needed by Chandan to complete the job alone, is
Let Chandan’s one-day work = x.
Then Bipin = 2x and Ankita = 4x.
All three work together for the first 20 days. Their combined daily work = $$x + 2x + 4x = 7x$$.
Work done in 20 days = $$20\times7x = 140x$$.
Bipin leaves after 20 days; Ankita and Chandan continue for the remaining (60-20=40) days.
Their combined daily work = $$4x + x = 5x$$. Work done in 40 days = $$40\times5x = 200x$$.
Total work = $$140x+200x=340x$$.
We know that Chandan does x work in a day. So, the number of days it takes him to finish the work is 340.
Answer: 340 days.
Renu would take 15 days working 4 hours per day to complete a certain task whereas Seema would take 8 days working 5 hours per day to complete the same task. They decide to work together to complete this task. Seema agrees to work for double the number of hours per day as Renu, while Renu agrees to work for double the number of days as Seema. If Renu works 2 hours per day, then the number of days Seema will work, is
Let us assign the amount of work done by Renu in one hour is R
And the amount of work done by Seema in one hour is S
We are told that a certain task with different time durations for Seema and Renu
Renu=15 days with 4 hours each day, that is total work done by Renu is $$15\times\ 4\times\ R=60R$$
Similarly for Seema, 8 days and 5 hours each day, total work done by Seema is $$40S$$
We know that $$60R=40S$$ or $$S=1.5R$$
For this task, let us assume that the amount of days that Seema decides to work is X and the hours per day that Renu decides to work is Y
We are then told that, Seema works for 2Y hours per day and Renu works for 2X days,
Work done by them will be $$2XYR$$ and $$2XYS$$
We are told that Y=2, Making this $$4XR$$ and $$4XS$$
$$S=1.5R$$
Total work will be, $$4XR$$+$$6XR$$=$$60R$$
We get the value of $$X=6$$
X is the number of days Seema will work, which is 6.
Sam can complete a job in 20 days when working alone. Mohit is twice as fast as Sam and thrice as fast as Ayna in the same job. They undertake a job with an arrangement where Sam and Mohit work together on the first day, Sam and Ayna on the second day, Mohit and Ayna on the third day, and this three-day pattern is repeated till the work gets completed. Then, the fraction of total work done by Sam is
We are given that Sam completes a piece of work in 20 days. We are also given that Mohit is twice as fast, so he should take only 10 days. Mohit is thrice as fast as Ayna, so he would take 30 days.
Let's take the total work to be 60 units; this would give the work done per day for Mohit, Sam, and Ayna to be 6, 3 and 2, respectively.
On the first day Sam and Mohit work: doing 9 units
On the second day Sam and Ayan work: doing 5 units
On the third day, Mohit and Ayan work: doing 8 units
Essentially doing 22 units in a 3 days cycle.
After two such cycles, there will be 60-44 = 16 units of work left
On day 7, Sam and Mohit would work 9 units, leaving 7 units
On day 8, Sam and Ayan would work 5 units, leaving 2 units
And on day 9, Ayan and Mohit would complete the remaining work.
So Sam worked for a total of 2+2+2= 6 days and on each day he did 3 units of work, completing 18 units of work.
The ratio of work done by Sam would be $$\frac{18}{60}=\frac{3}{10}$$
Therefore, Option B is the correct answer.
Amal and Vimal together can complete a task in 150 days, while Vimal and Sunil together can complete the same task in 100 days. Amal starts working on the task and works for 75 days, then Vimal takes over and works for 135 days. Finally, Sunil takes over and completes the remaining task in 45 days. If Amal had started the task alone and worked on all days, Vimal had worked on every second day, and Sunil had worked on every third day, then the number of days required to complete the task would have been
We can take the work done by Amal, Vimal and Sunil to be A, V and S, respectively.
Let's take the total work they did to be T.
We are given the equations:
150A + 150V = T ...(1)
100V + 100S = T ...(2)
75A + 135V + 45S = T ...(3)
Adding (1) and (2), we get: 150A + 250V + 100S = 2T ...(4)
And multiplying (3) with 2 we get: 150A + 270V + 100S = 2T ...(5)
Subtracting (5) from (4), we get 10S = 20V or simply S = 2V
Using this in (2), we get the total work T to be 300V, and using that result in (1), we get A=V
Therefore, the work done by A, V and S equals V, V, and 2V units per day.
Now, in the question, we are given work cycles. To simplify the calculations, we should consider a time duration that is the LCM of the period taken by the three agents, which in this case would be 6
In 6 days, Amal will work for 6 days, doing 6V units of work.
Vimal will work for 3 days, doing 3V units of work.
Sunil will work for 2 days, doing 4V units of work.
So, in one 6-day cycle, 13V units of work will be done.
Dividing the total work (300V) by 13V we can see that in 23 cycles 299V units of work will be done.
These 23 cycles will be $$23\times\ 6\ =\ 138$$ days
The remaining 1V units of work will be done the next day.
Therefore, a total of 139 days will be required.
Pipes A and C are fill pipes while Pipe B is a drain pipe of a tank. Pipe B empties the full tank in one hour less than the time taken by Pipe A to fill the empty tank. When pipes A, B and C are turned on together, the empty tank is filled in two hours. If pipes B and C are turned on together when the tank is empty and Pipe B is turned off after one hour, then Pipe C takes another one hour and 15 minutes to fill the remaining tank. If Pipe A can fill the empty tank in less than five hours, then the time taken, in minutes, by Pipe C to fill the empty tank is
Let the time taken by A to fill the tank alone be x hours, which implies the time taken by B to empty the tank alone is (x-1) hours (B is the drainage pipe), and the time taken by C to fill the tank is y hours.
It is given that when pipes A, B, and C are turned on together, the empty tank is filled in two hours.
Hence, $$\frac{1}{x}-\frac{1}{x-1}+\frac{1}{y}=\frac{1}{2}$$ .... Eq(1)
It is given that if pipes B and C are turned on together when the tank is empty and Pipe B is turned off after one hour, then Pipe C takes another one hour and 15 minutes to fill the remaining tank.
Hence, B worked for 1 hour, and C worked for 2 hours 15 minutes, which is equal to $$\frac{9}{4}$$ hours.
In 1 hour, B worked $$-\frac{1}{x-1}$$ units, and in $$\frac{9}{4}$$ hours, C worked $$\frac{9}{4y}$$ units.
Hence, $$\frac{9}{4y}-\frac{1}{x-1}=1$$ .... Eq(2)
Solving both equations, we get $$y=\frac{3}{2}$$, and $$x=3$$
Hence, the time taken by C is $$\frac{3}{2}$$ hours, which is equal to $$90$$ minutes.
The correct option is A
Rahul, Rakshita and Gurmeet, working together, would have taken more than 7 days to finish a job. On the other hand, Rahul and Gurmeet, working together would have taken less than 15 days to finish the job. However, they all worked together for 6 days, followed by Rakshita, who worked alone for 3 more days to finish the job. If Rakshita had worked alone on the job then the number of days she would have taken to finish the job, cannot be
Let the work done by Rahul, Rakshita, and Gurmeet be a, b, and c units per day, respectively, and the total units of work are W.
Hence, we can say that 7(a+b+c) < W ( Rahul, Rakshita, and Gurmeet, working together, would have taken more than 7 days to finish a job).
Similarly, we can say that 15(a+c) > W ( Rahul and Gurmeet, working together would have taken less than 15 days to finish the job)
Now, comparing these two inequalities, we get: 7(a+b+c) < W < 15(a+c)
It is also known that they all worked together for 6 days, followed by Rakshita, who worked alone for 3 more days to finish the job. Therefore, the total units of work done is: W = 6(a+b+c)+3b
Hence, we can say that 7(a+b+c) < 6(a+b+c)+3b < 15(a+c)
Therefore, (a+b+c) < 3b => a+c < 2b, and 9b < 9(a+c) => b < a+c
=> a+b+c < 3b => 7(a+b+c) < 21b , and 15b < 15(a+c)
Hence, The number of days required for b must be in between 15 and 21 (both exclusive).
Hence, the correct option is D
Gautam and Suhani, working together, can finish a job in 20 days. If Gautam does only 60% of his usual work on a day, Suhani must do 150% of her usual work on that day to exactly make up for it. Then, the number of days required by the faster worker to complete the job working alone is
Let 'g' and 's' be the efficiencies of Gautam and Suhani. Let W is the total amount of work.
=> g + s = W/20 (1 day work) ----(1)
Also Gautam doing only 60% => 3g/5 and Suhani doing 150% => 3s/2
=> 3g/5 + 3s/2 = W/20 (1 day work)
=> $$g+s=\dfrac{3g}{5}+\dfrac{3s}{2}$$
=> $$\dfrac{s}{g}=\dfrac{4}{5}$$ => Gautam is the more efficient person.
Now, from the 1st equation
=> $$g+\dfrac{4g}{5}=\dfrac{W}{20}$$
=> $$\dfrac{9}{5}g=\dfrac{W}{20}$$
=> $$g=\dfrac{W}{36}$$
=> Gautam takes 36 days to finish the complete work.
The amount of job that Amal, Sunil and Kamal can individually do in a day, are in harmonic progression. Kamal takes twice as much time as Amal to do the same amount of job. If Amal and Sunil work for 4 days and 9 days, respectively, Kamal needs to work for 16 days to finish the remaining job. Then the number of days Sunil will take to finish the job working alone, is
Let us assume the efficiencies of Amal, Sunil, and Kamal are a, s, and k, respectively.
Given that they are in H.P.
=> $$\dfrac{2}{s}=\dfrac{1}{a}+\dfrac{1}{k}$$ ---(1)
Also, given that Kamal takes twice as much time as Amal to do the same amount of job
=> a = 2k
Given that when Amal and Sunil work for 4 days and 9 days, respectively, Kamal needs to work for 16 days to finish the remaining job.
=> If W is the total work => 4a + 9s + 16k = W.
from (1)$$\dfrac{2}{s}=\dfrac{1}{a}+\dfrac{2}{a}$$ => $$a=\dfrac{3}{2}s$$ and $$k=\dfrac{3}{4}s$$
=> $$4\left(\dfrac{3s}{2}\right)+9s+16\left(\dfrac{3s}{4}\right)=W$$
=> $$6s+9s+12s=W$$
=> $$27s=W\ =>\ s\ =\ \dfrac{W}{27}$$
=> Sunil will take 27 days to finish the work when working alone.
A group of N people worked on a project. They finished 35% of the project by working 7 hours a day for 10 days. Thereafter, 10 people left the group and the remaining people finished the rest of the project in 14 days by working 10 hours a day. Then the value of N is
Let the unit of work done by 1 man in 1 hour and 1 day be 1 MDH unit (Man Day Hour).
Thus, in 7 hours per day for 10 days, the work done by N people =$$N\times\ 7\times\ 10$$ MDH units.
Since this is equal to 35% of the total work,
35% of the total work = $$N\times\ 7\times\ 10$$ MDH units.
Total work = $$\frac{\left(N\times\ 100\times\ 7\times\ 10\right)}{35}=200\times N$$ MDH units.
The work left = $$200N-70N=130N$$ MDH units.
Now, 10 people left the job. So, the number of people left = (N-10)
Since (N-10) people completed the rest of work in 14 days by working 10 hours a day,
$$(N-10)\times\ 14\times\ 10=130N$$
$$10N=1400$$
N = 140
Thus, the correct option is D.
Working alone, the times taken by Anu, Tanu and Manu to complete any job are in the ratio 5 : 8 : 10. They accept a job which they can finish in 4 days if they all work together for 8 hours per day. However, Anu and Tanu work together for the first 6 days, working 6 hours 40 minutes per day. Then, the number of hours that Manu will take to complete the remaining job working alone is
Let the time taken by Anu, Tanu and Manu be 5x, 8x and 10x hours.
Total work = LCM(5x, 8x, 10x) = 40x
Anu can complete 8 units in one hour
Tanu can complete 5 units in one hour
Manu can complete 4 units in one hour
It is given, three of them together can complete in 32 hours.
32(8 + 5 + 4) = 40x
x = $$\frac{68}{5}$$
It is given,
Anu and Tanu work together for the first 6 days, working 6 hours 40 minutes per day, i.e. 36 + 4 = 40 hours
40(8 + 5) + y(4) = 40x
4y = 24
y = 6
Manu alone will complete the remaining work in 6 hours.
Bob can finish a job in 40 days, if he works alone. Alex is twice as fast as Bob and thrice as fast as Cole in the same job. Suppose Alex and Bob work together on the first day, Bob and Cole work together on the second day, Cole and Alex work together on the third day, and then, they continue the work by repeating this three - day roster, with Alex and Bob working together on the fourth day, and so on. Then, the total number of days Alex would have worked when the job gets finished, is
Let the efficiency of Bob be 3 units/day. So, Alex's efficiency will be 6 units/day, and Cole's will be 2 units/day.
Since Bob can finish the job in 40 days, the total work will be 40*3 = 120 units.
Since Alex and Bob work on the first day, the total work done = 3 + 6 = 9 units.
Similarly, for days 2 and 3, it will be 5 and 8 units, respectively.
Thus, in the first 3 days, the total work done = 9 + 5 + 8 = 22 units.
The work done in the first 15 days = 22*5 = 110 units.
Thus, the work will be finished on the 17th day(since 9 + 5 = 14 units are greater than the remaining work).
Since Alex works on two days of every 3 days, he will work for 10 days out of the first 15 days.
Then he will also work on the 16th day.
The total number of days = 11.
One day, Rahul started a work at 9 AM and Gautam joined him two hours later. They then worked together and completed the work at 5 PM the same day. If both had started at 9 AM and worked together, the work would have been completed 30 minutes earlier. Working alone, the time Rahul would have taken, in hours, to complete the work is
Let Rahul work at a units/hr and Gautam at b units/hour
Now as per the condition :
8a+6b =7.5a+7.5b
so we get 0.5a=1.5b
or a=3b
Therefore total work = 8a +6b = 8a +2a =10a
Now Rahul alone takes 10a/10 = 10 hours.
Anu, Vinu and Manu can complete a work alone in 15 days, 12 days and 20 days, respectively. Vinu works everyday. Anu works only on alternate days starting from the first day while Manu works only on alternate days starting from the second day. Then, the number of days needed to complete the work is
Let the total amount of work be 60 units.
Then Anu, Vinu, and Manu do 4, 5, and 3 units of work per day respectively.
On the 1st day, Anu and Vinu work. Work done on the 1st day = 9 units
On the 2nd day, Manu and Vinu work. Work done on the 2nd day = 8 units
This cycle goes on. And in 6 days, the work completed is 9+8+9+8+9+8 = 51 units.
On the 7th day, again Anu and Vinu work and complete the remaining 9 units of work. Thus, the number of days taken is 7 days.
Anil can paint a house in 60 days while Bimal can paint it in 84 days. Anil starts painting and after 10 days, Bimal and Charu join him. Together, they complete the painting in 14 more days. If they are paid a total of ₹ 21000 for the job, then the share of Charu, in INR, proportionate to the work done by him, is
Let Entire work be W
Now Anil worked for 24 days
Bimal worked for 14 days and Charu worked for 14 days .
Now Anil Completes W in 60 days
so in 24 days he completed 0.4W
Bimal completes W in 84 Days
So in 14 Days Bimal completes = $$\frac{W}{6}$$
Therefore work done by charu = $$W-\frac{W}{6}-\frac{4W}{10}$$= $$\frac{26W}{10}$$=$$\frac{13W}{30}$$
Therefore proportion of Charu = $$\frac{13}{30}\times\ 21000$$=9100
Amar, Akbar and Anthony are working on a project. Working together Amar and Akbar can complete the project in 1 year, Akbar and Anthony can complete in 16 months, Anthony and Amar can complete in 2 years. If the person who is neither the fastest nor the slowest works alone, the time in months he will take to complete the project is
Let the total work be 48 units. Let Amar do 'm' work, Akbar do 'k' work, and Anthony do 'n' units of work in a month.
Amar and Akbar complete the project in 12 months. Hence, in a month they do $$\frac{48}{12}$$=4 units of work.
m+k = 4.
Similarly, k+n = 3, and m+n = 2.
Solving the three equations, we get $$m=\frac{3}{2},\ k=\frac{5}{2},\ n=\frac{1}{2}$$.
Here, Amar works neither the fastest not the slowest, and he does 1.5 units of work in a month. Hence, to complete the work, he would take $$\frac{48}{1.5}=32$$months.
Anil can paint a house in 12 days while Barun can paint it in 16 days. Anil, Barun, and Chandu undertake to paint the house for ₹ 24000 and the three of them together complete the painting in 6 days. If Chandu is paid in proportion to the work done by him, then the amount in INR received by him is
Now Anil Paints in 12 Days
Barun paints in 16 Days
Now together Arun , Barun and Chandu painted in 6 Days
Now let total work be W
Now each worked for 6 days
So Anil's work = 0.5W
Barun's work = $$\frac{6W}{16}=\frac{3W}{8}$$
Therefore Charu's work = $$\frac{W}{2}-\frac{3W}{8}=\ \frac{W}{8}$$
Therefore proportion of charu =$$\frac{24000}{8}=\ 3,000$$
Two pipes A and B are attached to an empty water tank. Pipe A fills the tank while pipe B drains it. If pipe A is opened at 2 pm and pipe B is opened at 3 pm, then the tank becomes full at 10 pm. Instead, if pipe A is opened at 2 pm and pipe B is opened at 4 pm, then the tank becomes full at 6 pm. If pipe B is not opened at all, then the time, in minutes, taken to fill the tank is
Let A fill the tank at x liters/hour and B drain it at y liters/hour
Now as per Condition 1 :
We get Volume filled till 10pm = 8x-7y (1) .
Here A operates for 8 hours and B operates for 7 hours .
As per condition 2
We get Volume filled till 6pm = 4x-2y (2)
Here A operates for 4 hours and B operates for 2 hours .
Now equating (1) and (2)
we get 8x-7y =4x-2y
so we get 4x =5y
y =4x/5
So volume of tank = $$8x-7\times\ \frac{4x}{5}=\frac{12x}{5}$$
So time taken by A alone to fill the tank = $$\frac{\frac{12x}{5}}{x}=\frac{12}{5}hrs\ $$
= 144 minutes
John takes twice as much time as Jack to finish a job. Jack and Jim together take one-thirds of the time to finish the job than John takes working alone. Moreover, in order to finish the job, John takes three days more than that taken by three of them working together. In how many days will Jim finish the job working alone?
Let Jack take "t" days to complete the work, then John will take "2t" days to complete the work. So work done by Jack in one day is (1/t) and John is (1/2t) .
Now let Jim take "m" days to complete the work. According to question, $$\frac{1}{t}+\frac{1}{m}=\frac{3}{2t}\ or\ \frac{1}{m}=\frac{1}{2t\ }or\ m=2t$$ Hence Jim takes "2t" time to complete the work.
Now let the three of them complete the work in "p" days. Hence John takes "p+3" days to complete the work.
$$\frac{1}{2t}\left(m+3\right)=\left(\frac{4}{2t}\right)m$$
$$\frac{1}{2t}\left(m+3\right)=\left(\frac{4}{2t}\right)m$$
or m=1. Hence JIm will take (1+3)=4 days to complete the work. Similarly John will also take 4 days to complete the work
A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?
Let the desired efficiency of each worker '6x' per day.
140*6x*200= 6 km ...(i)
In 60 days 60/200*6=1.8 km of work is to be done but actually 1.5km is only done.
Actual efficiency 'y'= 1.5/1.8 *6x =5x.
Now, left over work = 4.5km which is to be done in 140 days with 'n' workers whose efficiency is 'y'.
=> n*5x*140=4.5 ...(ii)
(i)/(ii) gives,
$$\frac{\left(140\cdot6x\cdot200\right)}{\left(n\cdot5x\cdot140\right)}=\frac{6}{4.5}$$
=> n=180.
.'. Extra 180-140 =40 workers are needed.
At their usual efficiency levels, A and B together finish a task in 12 days. If A had worked half as efficiently as she usually does, and B had worked thrice as efficiently as he usually does, the task would have been completed in 9 days. How many days would A take to finish the task if she works alone at her usual efficiency?
Assuming A completes a units of work in a day and B completes B units of work in a day and the total work = 1 unit
Hence, 12(a+b)=1.........(1)
Also, 9($$\ \frac{\ a}{2}$$+3b)=1 .........(2)
Using both equations, we get, 12(a+b)= 9($$\ \frac{\ a}{2}$$+3b)
=> 4a+4b=$$\ \frac{\ 3a}{2}$$+9b
=> $$\ \frac{\ 5a}{2}$$=5b
=> a=2b
Substituting the value of b in equation (1),
12($$\ \frac{\ 3a}{2}$$)=1
=> a=$$\ \frac{\ 1}{18}$$
Hence, the number of days required = 1/($$\ \frac{\ 1}{18}$$)=18
Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?
Consider the work done by a man in a day = a and that by a machine = b
Since, three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job, hence the efficiency will be double.
=> 3a+8b = 2(3b+8a)
=> 13a=2b
Hence work done by 13 men in a day = work done by 2 machines in a day.
=> If two machines can finish the job in 13 days, then same work will be done 13 men in 13 days.
Hence the required number of men = 13
Anil alone can do a job in 20 days while Sunil alone can do it in 40 days. Anil starts the job, and after 3 days, Sunil joins him. Again, after a few more days, Bimal joins them and they together finish the job. If Bimal has done 10% of the job, then in how many days was the job done?
Let the total work be LCM of 20, 40 = 40 units
Efficiency of Anil and Sunil is 2 units and 1 unit per day respectively.
Anil works alone for 3 days, so Anil must have completed 6 units.
Bimal completes 10% of the work while working along with Anil and Sunil.
Bimal must have completed 4 units.
The remaining 30 units of work is done by Anil and Sunil
Number of days taken by them 30/3=10
The total work is completed in 3+10=13 days
A water tank has inlets of two types A and B. All inlets of type A when open, bring in water at the same rate. All inlets of type B, when open, bring in water at the same rate. The empty tank is completely filled in 30 minutes if 10 inlets of type A and 45 inlets of type B are open, and in 1 hour if 8 inlets of type A and 18 inlets of type B are open. In how many minutes will the empty tank get completely filled if 7 inlets of type A and 27 inlets of type B are open?
Let the efficiency of type A pipe be 'a' and the efficiency of type B be 'b'.
In the first case, 10 type A and 45 type B pipes fill the tank in 30 mins.
So, the capacity of the tank = $$\dfrac{1}{2}$$(10a + 45b)........(i)
In the second case, 8 type A and 18 type B pipes fill the tank in 1 hour.
So, the capacity of the tank = (8a + 18b)..........(ii)
Equating (i) and (ii), we get
10a + 45b = 16a + 36b
=>6a = 9b
From (ii), capacity of the tank = (8a + 18b) = (8a + 12a) = 20a
In the third case, 7 type A and 27 type B pipes fill the tank.
Net efficiency = (7a + 27b) = (7a + 18a) = 25a
Time taken = $$\dfrac{20\text{a}}{25\text{a}}$$ hour = 48 minutes.
Hence, 48 is the correct answer.
Humans and robots can both perform a job but at different efficiencies. Fifteen humans and five robots working together take thirty days to finish the job, whereas five humans and fifteen robots working together take sixty days to finish it. How many days will fifteen humans working together (without any robot) take to finish it?
Let the efficiency of humans be 'h' and the efficiency of robots be 'r'.
In the first case,
Total work = (15h + 5r) * 30......(i)
In the second case,
Total work = (5h + 15r) * 60......(ii)
On equating (i) and (ii), we get
(15h + 5r) * 30 = (5h + 15r) * 60
Or, 15h + 5r = 10h + 30r
Or, 5h = 25r
Or, h = 5r
Total work = (15h + 5r) * 30 = (15h + h) * 30 = 480h
Time taken by 15 humans = $$\dfrac{\text{480h}}{\text{15h}}$$ days= 32 days.
Hence, option C is the correct answer.
When they work alone, B needs 25% more time to finish a job than A does. They two finish the job in 13 days in the following manner: A works alone till half the job is done, then A and B work together for four days, and finally B works alone to complete the remaining 5% of the job. In how many days can B alone finish the entire job?
Let us assume that A can complete 'a' units of work in a day and B can complete 'b' units of work in a day.
A works alone till half the work is completed.
A and B work together for 4 days and B works alone to complete the last 5% of the work.
=> A and B in 4 days can complete 45% of the work.
Let us assume the total amount of work to be done to be 100 units.
4a + 4b = 45 ---------(1)
B needs 25% more time than A to finish a job.
=> 1.25*b = a ----------(2)
Substituting (2) in (1), we get,
5b+4b = 45
9b = 45
b = 5 units/day
B alone can finish the job in 100/5 = 20 days.
Therefore, option A is the right answer.
A tank is emptied everyday at a fixed time point. Immediately thereafter, either pump A or pump B or both start working until the tank is full. On Monday, A alone completed filling the tank at 8 pm. On Tuesday, B alone completed filling the tank at 6 pm. On Wednesday, A alone worked till 5 pm, and then B worked alone from 5 pm to 7 pm, to fill the tank. At what time was the tank filled on Thursday if both pumps were used simultaneously all along?
Let 't' pm be the time when the tank is emptied everyday. Let 'a' and 'b' be the liters/hr filled by pump A and pump B respectively.
On Monday, A alone completed filling the tank at 8 pm. Therefore, we can say that pump A worked for (8 - t) hours. Hence, the volume of the tank = a*(8 - t) liters.
Similarly, on Tuesday, B alone completed filling the tank at 6 pm. Therefore, we can say that pump B worked for (6 - t) hours. Hence, the volume of the tank = b*(6 - t) liters.
On Wednesday, A alone worked till 5 pm, and then B worked alone from 5 pm to 7 pm, to fill the tank. Therefore, we can say that pump A worked for (5 - t) hours and pump B worked for 2 hours. Hence, the volume of the tank = a*(5 - t)+2b liters.
We can say that a*(8 - t) = b*(6 - t) = a*(5 - t) + 2b
a*(8 - t) = a*(5 - t) + 2b
$$\Rightarrow$$ 3a = 2b ... (1)
a*(8 - t) = b*(6 - t)
Using equation (1), we can say that
$$a*(8-t)=\dfrac{3a}{2}\times(6-t)$$
$$t = 2$$
Therefore, we can say that the tank gets emptied at 2 pm daily. We can see that A takes 6 hours and pump B takes 4 hours alone.
Hence, working together both can fill the tank in = \dfrac{6*4}{6+4} = 2.4 hours or 2 hours and 24 minutes.
The pumps started filling the tank at 2:00 pm. Hence, the tank will be filled by 4:24 pm.
A tank is fitted with pipes, some filling it and the rest draining it. All filling pipes fill at the same rate, and all draining pipes drain at the same rate. The empty tank gets completely filled in 6 hours when 6 filling and 5 draining pipes are on, but this time becomes 60 hours when 5 filling and 6 draining pipes are on. In how many hours will the empty tank get completely filled when one draining and two filling pipes are on?
Let the efficiency of filling pipes be 'x' and the efficiency of draining pipes be '-y'.
In the first case,
Capacity of tank = (6x - 5y) * 6..........(i)
In the second case,
Capacity of tank = (5x - 6y) * 60.....(ii)
On equating (i) and (ii), we get
(6x - 5y) * 6 = (5x - 6y) * 60
or, 6x - 5y = 50x - 60y
or, 44x = 55y
or, 4x = 5y
or, x = 1.25y
Capacity of the tank = (6x - 5y) * 6 = (7.5y - 5y) * 6 = 15y
Net efficiency of 2 filling and 1 draining pipes = (2x - y) = (2.5y - y) = 1.5y
Time required = $$\dfrac{\text{15y}}{\text{1.5y}}$$hours = 10 hours.
Hence, 10 is the correct answer.
Ramesh and Ganesh can together complete a work in 16 days. After seven days of working together, Ramesh got sick and his efficiency fell by 30%. As a result, they completed the work in 17 days instead of 16 days. If Ganesh had worked alone after Ramesh got sick, in how many days would he have completed the remaining work?
Let 'R' and 'G' be the amount of work that Ramesh and Ganesh can complete in a day.
It is given that they can together complete a work in 16 days. Hence, total amount of work = 16(R+G) ... (1)
For first 7 days both of them worked together. From 8th day, Ramesh worked at 70% of his original efficiency whereas Ganesh worked at his original efficiency. It took them 17 days to finish the same work. i.e. Ramesh worked at 70% of his original efficiency for 10 days.
$$\Rightarrow$$ 16(R+G) = 7(R+G)+10(0.7R+G)
$$\Rightarrow$$ 16(R+G) = 14R+17G
$$\Rightarrow$$ R = 0.5G ... (2)
Total amount of work left when Ramesh got sick = 16(R+G) - 7(R+G) = 9(R+G) = 9(0.5+G) = 13.5G
Therefore, time taken by Ganesh to complete the remaining work = $$\dfrac{13.5G}{G}$$ = 13.5 days.
A person can complete a job in 120 days. He works alone on Day 1. On Day 2, he is joined by another person who also can complete the job in exactly 120 days. On Day 3, they are joined by another person of equal efficiency. Like this, everyday a new person with the same efficiency joins the work. How many days are required to complete the job?
Let the rate of work of a person be x units/day. Hence, the total work = 120x.
It is given that one first day, one person works, on the second day two people work and so on.
Hence, the work done on day 1, day 2,... will be x, 2x, 3x, ... respectively.
The sum should be equal to 120x.
$$120x = x* \frac{n(n+1)}{2}$$
$$n^2 + n - 240 = 0$$
n = 15 is the only positive solution.
Hence, it takes 15 days to complete the work.
A tank has an inlet pipe and an outlet pipe. If the outlet pipe is closed then the inlet pipe fills the empty tank in 8 hours. If the outlet pipe is open then the inlet pipe fills the empty tank in 10 hours. If only the outlet pipe is open then in how many hours the full tank becomes half-full?
Let the time taken by the outlet pipe to empty = x hours
Then, $$\frac{1}{8} - \frac{1}{x} = \frac{1}{10}$$
=> $$x = 40$$
Hence time taken by the outlet pipe to make the tank half-full = 40/2 = 20 hour
Amal can complete a job in 10 days and Bimal can complete it in 8 days. Amal, Bimal and Kamal together complete the job in 4 days and are paid a total amount of Rs 1000 as remuneration. If this amount is shared by them in proportion to their work, then Kamal's share, in rupees, is
Let the time take by kamal to complete the task be x days.
Hence we have $$\frac{1}{10} + \frac{1}{8} + \frac{1}{x} = \frac{1}{4}$$
=> x = 40 days.
Ratio of the work done by them = $$\frac{1}{10} : \frac{1}{8} : \frac{1}{40}$$ = 4 : 5 : 1
Hence the wage earned by Kamal = 1/10 * 1000 = 100
A chemical plant has four tanks (A, B, C, and D), each containing 1000 litres of a chemical. The chemical is being pumped from one tank to another as follows:
From A to B @ 20 litres/minute
From C to A @ 90 litres/minute
From A to D @ 10 litres/minute
From C to D @ 50 litres/minute
From B to C @ 100 litres/minute
From D to B @ 110 litres/minute
Which tank gets emptied first, and how long does it take (in minutes) to get empty after pumping starts?
After 1 min the cans will contain following amount of chemicals : A - 1060 B - 1030 C - 970 D - 950
So, we can see that the can D loses 50 ltrs in 1 min which is highest. So the can D will lose 1000 ltrs in 20*1 = 20 mins.
It takes six technicians a total of 10 hr to build a new server from Direct Computer, with each working at the same rate. If six technicians start to build the server at 11 am, and one technician per hour is added beginning at 5 pm, at what time will the server be completed?
[CAT 2002]
Let the work done by each technician in one hour be 1 unit.
Therefore, total work to be done = 60 units.
From 11 AM to 5 PM, work done = 6*6 = 36 units.
Work remaining = 60 - 36 = 24 units.
Work done in the next 3 hours = 7 units + 8 units + 9 units = 24 units.
Therefore, the work gets done by 8 PM.
Three small pumps and a large pump are filling a tank. Each of the three small pump works at 2/3 the rate of the large pump. If all four pumps work at the same time, they should fill the tank in what fraction of the time that it would have taken the large pump alone?
Let the work done by the big pump in one hour be 3 units.
Therefore, work done by each of the small pumps in one hour = 2 units.
Let the total work to be done in filling the tank be 9 units.
Therefore, time taken by the big pump if it operates alone = 9/3 = 3 hours.
If all the pumps operate together, the work done in one hour = 3 + 2*3 = 9 units.
Together, all of them can fill the tank in 1 hour.
Required ratio = 1/3
A can complete a piece of work in 4 days. B takes double the time taken by A, C takes double that of B, and D takes double that of C to complete the same task. They are paired in groups of two each. One pair takes two-thirds the time needed by the second pair to complete the work. Which is the first pair?
A takes 4 days to complete the work.
So, B takes 8 days to complete the same work.
C takes 16 days to complete the work.
D takes 32 days to complete the same work.
In order to measure, let the total work be of 64 units. Hence, the speed of working of each of the four persons is given below.
A - 16 units/hr
B - 8 units/hr
C - 4 units/hr
D - 2 units/hr
From the given options, we need to find two pairs in such a way that their speeds are in the ratio 3:2. Note that A+D=18 while B+C=12 and the ratio is 3:2
Hence, the first pair is A and D and the second pair is B and C
There’s a lot of work in preparing a birthday dinner. Even after the turkey is in the oven, there’s still the potatoes and gravy, yams, salad, and cranberries, not to mention setting the table.
Three friends — Asit, Arnold and Afzal — work together to get all of these chores done. The time it takes them to do the work together is 6 hr less than Asit would have taken working alone, 1 hr less than Arnold would have taken alone, and half the time Afzal would have taken working alone. How long did it take them to do these chores working together?
Let the time taken working together be t.
Time taken by Arnold = t+1
Time taken by Asit = t+6
Time taken by Afzal = 2t
Work done by each person in one day = $$\frac{1}{(t+1)}+\frac{1}{(t+6)}+\frac{1}{2t}$$
Total portion of workdone in one day $$=\frac{1}{t}$$
$$\frac{1}{(t+1)}+\frac{1}{(t+6)}+\frac{1}{2t}=\frac{1}{t}$$
$$\frac{1}{(t+1)}+\frac{1}{(t+6)}=\frac{2-1}{2t}$$
$$2t+7=\frac{(t+1)\cdot(t+6)}{2t}$$
$$3t^2-7t+6=0 \longrightarrow\ t=\frac{2}{3} $$or $$t=-3$$
Therefore total time = $$\frac{2}{3}$$hours = 40mins
Alternatively,
$$\frac{1}{(t+1)}+\frac{1}{(t+6)}+\frac{1}{2t}=\frac{1}{t}$$
From the options, if time $$= 40$$ min, that is, $$t = \frac{2}{3}$$
LHS = $$\frac{3}{5} + \frac{3}{20} + \frac{3}{4} = \frac{(12+3+15)}{20} = \frac{30}{20} = \frac{3}{2}$$
RHS = $$\frac{1}{t}=\frac{3}{2}$$
The equation is satisfied only in case of option C
Hence, C is correct
A company has a job to prepare certain number cans and there are three machines A, B and C for this job. A can complete the job in 3 days, B can complete the job in 4 days, and C can complete the job in 6 days. How many days will the company take to complete the job if all the machines are used simultaneously?
If they work together, then total work done in single day = $$\frac{1}{3} + \frac{1}{4} + \frac{1}{6} = \frac{9}{12}$$
So $$\frac{9}{12}$$ work is done in 1 day
Hence unit work will be done in $$\frac{12}{9}$$ or $$\frac{4}{3}$$ days.
Raja starts working on February 25(Sunday), 1996, and finishes the job on March 2, 1996. How much time would T and J take to finish the same job if both start on the same day as Raja?
Raja takes 7 days to complete the job.
Feb 25, 1996 is a Sunday.
If T and J start working on Sunday, they can complete the work by wednesday because T would have worked for 3 days and J would worked for 4 days, thereby matching the number of days worked by Raja.
Hence, they can complete the job in 4 days.
Starting on February 25, 1996 (Sunday), if Raja had finished his job on April 2, 1996, when would T and S together likely to have completed the job, had they started on the same day as Raja?
The number of days taken by Raja to complete the work is 5+31+2 = 38
So, cumulative number of days needed by T and S to complete the work is 38.
Both of them take two days off in a week as S takes of on Saturday and Sunday and T takes off on Tuesday and Thursday.
So, total number of man-working days per week by the duo is 10.
Hence, after three weeks, they finish 30 man working days.
i.e by end of 17th March 1996 (Sunday), 30 man working days are finished.
Both of them work on Monday,
S works on Tuesday
Both of them work on Wednesday
S works on Thursday
Both of them work on Friday and the remaining 8 man working days are also over.
Hence, the required date is 17+5 = 22 March 1996 (Friday)
Alord got an order from a garment manufacturer for 480 Denim Shirts. He brought 12 sewing machines and appointed some expert tailors to do the job. However, many didn't report to duty. As a result, each of those who did, had to stitch 32 more shirts than originally planned by Alord, with equal distribution of work. How many tailors had been appointed earlier and how many had not reported for work?
Suppose he appointed x persons and y of them didn't come. Hence work done by each of them increases by 32.
So $$\frac{480}{x-y} - \frac{480}{x} = 32$$
Now we can check options by putting in the above eq.
x=10 and y=4 will be our answer
Three machines, A, B and C can be used to produce a product. Machine A will take 60 hours to produce a million units. Machine B is twice as fast as Machine A. Machine C will take the same amount of time to produce a million units as A and B running together. How much time will be required to produce a million units if all the three machines are used simultaneously?
As machine B's efficiency is twice as of A's, Hence, it will complete its work in 30 hours.
And C's efficiency is putting A and B together i.e. = 20 hours $$( (\frac{1}{60} + \frac{1}{30})^{-1})$$
Now if all three work together, then it will be completed in x (say) days.
$$\frac{1}{x} = \frac{1}{20} + \frac{1}{30} + \frac{1}{60}$$
or x = 10 hours
A, B and C individually can finish a work in 6, 8 and 15 hours respectively. They started the work together and after completing the work got Rs.94.60 in all. When they divide the money among themselves, A, B and C will respectively get (in Rs.)
Money will be distributed in the ratio of work done in an hour.
i.e. $$\frac{1}{6} : \frac{1}{8} : \frac{1}{15}$$
or 20:15:8
Hence part of A will be = $$\frac{20}{43} \times 94.6 = 44$$
part of B will be = $$\frac{15}{43} \times 94.6 = 33$$
part of C will be = $$\frac{8}{43} \times 94.6 = 17.60$$