A can do a work in 21 days and B in 42 days. If they work on it together for 7 days, then what fraction of work is left?
A will do in 7 days =(7/21)=1/3.
B will do in 7 days =(7/42)=1/6.
So, work left =(1-1/3-1/6)=3/6=1/2.
D is correct choice.