Directions for the following five questions: Answer the questions based on the two graphs shown below.
Figure I (the chart on the left) shows the amount of work distribution, in man-hours, for a software company between offshore and onsite activities.
Figure 2 (the chart on the right) shows the estimated and actual work effort involved in the different offshore activities in the same company during the same period.
[Note: Onsite refers to work performed at the customer’s premise and offshore refers to work performed at the developer’s premise.]
Total number of man-hours needed for the entire work to be done = 100+75+425+100+300+150 = 1150
Man-hours spent onsite = 75+100+150 = 325
So, required percentage = 325/1150 * 100% = 13/46 * 100% = 28.26% = 30% approx