X and Y together can do a piece of work in 30 days. Y and Z together can do the work in 20 days. X starts the work and works for 15 days then Y takes that work and works for 27 days. Finally Z finishes the remaining work in 9 days. In how many days Y alone can complete the entire work?

3

Riya Chugh 6y ago

60days

Ravi shankar 6y ago

Alone work X. 60 days Y. 60 days Z 30 days.

Jaideep Rathee 6y ago

60