Two men and four women can complete a piece of work in four days. One man and two women take the same time as five women to complete the work. Find the time taken by one woman to complete the work.

2

Bhushan Badgujjar 10y ago

10 days?

Ajith Neelakantan 10y ago

2m+4w=4
8m+16w =1

1m+2w=5w => 1m=3w

24w+16w=1 => 40w=1 and w=1/40

so 1 woman will take 40 days

So