Edit MetaData
5Â years, 4Â months ago
to do a certain work a and b work on alternate days, with b beginning the work on the first day. a can alone finish the work in 48 days. of the work gets completed in 34/3 days then b alone can finish the 4 times work in ?
Quick, Easy and Effective Revision
By proceeding you agree to create your account
Free CAT Formulas PDF will be sent to your email address soon !!!