ram Ek kam ko 10 din me krta hai aur Mohan 15 din krta hai. Dono milkr usi kam ko Kitne din me krege
4Â years, 3Â months ago
In terms of efficency
L.C.M of 10 & 15 is 30. So, 30 units of work need to be done.
eff. of ram is 3units/day & eff. of mohan is 2units/day.
together their eff. is 5 units/day.
total units of work is 30 units. It will take 30/5 = 6 days to complete
4Â years, 3Â months ago
Ram-1/10
Mohan-1/15
Both will complete the work in 1/10+1/15 = 1/6
Thus, Ram and Mohan will complete the work in 6 days.