can do a piece of work in 8 hours and B can do the same work in 12 hours. In how much time both can finish the whole work working together?

3

Arthur Joshu 7y ago

A's work in 1hr=1/8 ; B's work in 1hr=1/12

Total work in 1hr=1/8+1/12

                          =10/48 in 1hr

total time taken=48/10=4.8hrs


Paras Mittal 7y ago

efficiency varies inversely with time so A efficiency - 12 B efficiency -8 total work= 12*8 time taken by both= total work/ total efficiency of A and B time= 12*8/20 time = 4.8hrs

nandini 7y ago

A+B = (8×12)/(8+12) =96/20 =24/5 =4. 4/5 days. i.e, four four by five days.