a works twice as fast as B and B works twice as fast as C. all the three working together can finish a task in 4 days with the help of D. if D alone can finish the same task in 16 days then in how many days will A alone finish 75% of the same work

4

Rishabh Chhikara 6y ago

144/7 days

Bishal Borah 6y ago

7 days

I'm GROOT 6y ago

A will take 7 days to complete the whole work. But to complete 75% of the work A needs only 21/4 = 5.25 days.

Arijit Das 6y ago

21/4 for 75% work. 7 days for entire work