A does half as much work as B in three-fourth of the time.If together they take 18 days to complete the work,how much time shall B take to do it? (a)30 days (b)35 days (c)40 days (d)None of the With solution plz📝

2

Vishal Bhadane 6y ago

40 days

Kartikay Gupta 5y ago

30.. B takes X days to complete the work A will take 2×3/4x=3/2X So 1/X+ 2/3X=1/18 3+2=X/6 X=30