A can do a certain job in 12 days.B is 60% more efficient than A. How many days does B alone take to do rhe same job?

11

Narender Reddy 8y ago

,

Narender Reddy 8y ago

7.5 days

Sumit Kumar 8y ago

60% means 3/5 ; if  we consider 8 unit work then A do 3 unit, B do 5 unit. so in 12 days A can do 60 unit of work, and this 60 unit can be done by B in 60/8 days i.e 7.5 Days Answer.

Sumit Kumar 8y ago

it will be like, A=5 and B=8 unit per day.  

KRITI SHUKLA 8y ago

7.5 days


Suman Rockz 8y ago

7(1/2 ) days

Shiv Shubham 8y ago

7.5

Noshin Mev 8y ago

if A suppose 100% efficient than definetly B will be 160% efficient so if A takes 1/12 days to do a piece of work than B alone can do it in (160/100)*1/12 days that means 8/5*1/12 = 2/15 hence B can do it in 15/2 days that is 7.5 days

Teju 6y ago

7 1/2

Ashutosh Hota 5y ago

7,5 days

arpita jena 5y ago

7.5 days