A, B and C can complete a work in 20, 24 and 30 days respec tively. All of them starts to gether but after 4 days A leaves the job and B left the job 6 days before the work was completed. C completed the remaining work alone. In how many days was the total work completed?

1

Roranoa Zoro 5y ago

LCM of 20,24 and 30 is 120 unit (required work) A's 1-day work 120/20 = 6 unit per day B's 1-day work 120/24 = 5 unit per day C's 1-day work 120/30 = 4 unit per day A+B+C =15 unit per day, work for 4 day = 15*4= 60, left work 120-60=60unit now A leaves and B will leave 6 before work completed and the rest work is done by C let C takes t day's to finish the after A leave then C work done = 4*t and B's work done 5(t-6) 4*t + 5(t-6) = 60 on solving we get, t= 10 Total days 10+4=14