A and B together can do a piece of work in 20 days. A having worked for 8 days, B finishes the remaining work alone in 22 days. In how many days shall B finish the whole work alone? a)30 days B)20 1/3 days C)26 2/3 days D)40days

2

pradip malode 9y ago

if b 60% work done within 22 day then 100% work he will done within 36. 2/3

Bhagyashri Chavan 8y ago

C