48 men are employed to construct a building in 75 days . Due to some reason they wanted the building to be ready in 60 days. How many men should be employed to construct the building in 60 days

2

ujjawal kumar 5y ago

total man day required =48*75 no of ma required to build in 60 days =total man days /no of man given =48*75/60

Joydip Das 5y ago

78 ?