Instructions

The table below shows the estimated cost (in Rs. Lakh) of a project of laying a railway line between two places.


Question 66

After preparing the estimate, the provision for contingencies is felt inadequate and is therefore doubled. By what percent does the total estimate increase?

Solution

Total estimated cost before increment = 52.1+267.5+196.4+209.5 = 725.5

Increment in contingencies will be = 25.2

Hence, total estimated cost will also be increased with the same amount.

So percentage increment in total estimated cost will be = $$\frac{25.2}{725.5} \times 100 = 3.47$$

Video Solution

video

Your Doubts

Ask a Doubt (know more)

Drop Your File Here!

** You can Drag and Drop an Image in the above textarea
add image

Create a FREE account and get:

  • All Quant CAT complete Formulas and shortcuts PDF
  • 38+ CAT previous year papers with video solutions PDF
  • 5000+ Topic-wise Previous year CAT Solved Questions for Free

cracku

Boost your Prep!

Download App