The table below shows the estimated cost (in Rs. Lakh) of a project of laying a railway line between two places.


Question 62

If the length of the line to be laid each year is proportional to the estimated cost for cement, steel, bricks, building material and labour, what fraction of the total length is proposed to be completed by the third year?

Solution

Till third year expense was 407.1 and total expenditure is 597.1

So ratio will be $$\frac{407.1}{597.1}$$ = 0.7
That will be fraction of length which is supposed to be completed by third year