Work - Efficiency

Very Important

  • Efficiency * Total time taken = Total work
    Assume the total work to be 1 unit.

    If X can do the work in 'n' days, the fraction of work(efficiency) X does in a day is $$\frac{1}{n}$$ units/day.
  • If X can do the work in 'x' days, and Y can do the work in 'y' days, the number of days taken by both of them together to do the work is $$\frac{x*y}{x+y}$$
  • If $$A_1$$ men can do $$B_1$$ work in $$C_1$$ days and $$A_2$$ men can do $$B_2$$ work in $$C_2$$ days, then $$\frac{A_1 C_1}{B_1}$$ =$$\frac{A_2 C_2}{B_2}$$

    Note: 
    To simplify calculations, we try to get efficiencies as integers. We assume the total work to be some integral multiple of the total time taken. 

    Example:
    If X can do a work in 15 days and Y can do it in 12 days. Find the total days required to complete the work if X and Y both are working together.

    Sol
    . We assume the work to be LCM(15,12)=60 units to get the efficiencies of both X and Y in integers.
           Efficiency of X$$=\dfrac{60}{15}=4$$ units/day. 

           Efficiency of Y$$=\dfrac{60}{12}=5$$ units/day.
           So, when they work together the efficiencies would add up$$=4+5=9$$units/day.
           Let the time required to complete the work by X and Y together$$=a$$.
           So, $$9a=60$$.   $$a=\dfrac{60}{9}$$ days.

Formula Video


Question 1

Anu, Vinu and Manu can complete a work alone in 15 days, 12 days and 20 days, respectively. Vinu works everyday. Anu works only on alternate days starting from the first day while Manu works only on alternate days starting from the second day. Then, the number of days needed to complete the work is

Question 2

Amar, Akbar and Anthony are working on a project. Working together Amar and Akbar can complete the project in 1 year, Akbar and Anthony can complete in 16 months, Anthony and Amar can complete in 2 years. If the person who is neither the fastest nor the slowest works alone, the time in months he will take to complete the project is

Question 3

Anil can paint a house in 60 days while Bimal can paint it in 84 days. Anil starts painting and after 10 days, Bimal and Charu join him. Together, they complete the painting in 14 more days. If they are paid a total of ₹ 21000 for the job, then the share of Charu, in INR, proportionate to the work done by him, is

Log in to view all questions

Go back to topics

Join CAT 2026 course by 5-Time CAT 100%iler

Crack CAT 2026 & Other Exams with Cracku!