Instructions

The table below shows the estimated cost (in Rs. Lakh) of a project of laying a railway line between two places.


Question 64

If the cost of materials ((cement, steel, bricks, building materials) rises by 5% each year from 1990 onwards, by how much will the estimated cost rise for the years 1990 and 1991?

Solution

In the year 1990, total increment will be 4+2.25+0.6+0.9 = 7.75
And in the year 1991, total increment be 3.75+3+0.8+1.05=8.60
Hence total increase in estimated cost will be = 16.35 Lakhs

Video Solution

video

Create a FREE account and get:

  • All Quant CAT complete Formulas and shortcuts PDF
  • 35+ CAT previous year papers with video solutions PDF
  • 5000+ Topic-wise Previous year CAT Solved Questions for Free

cracku

Boost your Prep!

Download App