Three pipes P, Q and R can fill a tank in 6 hours. After working at it together for 2 hours, R is closed and both P and Q can fill the remaining part in 7 hours. The number of hours that will be taken by R alone to fill the tank is
CMAT Time and Work Questions
CMAT Time and Work Questions
It is given that P, Q and R together can complete the work in 6 hrs.
P, Q and R together worked for 2 hours, this implies they completed 1/3rd of the work.
R left and remaining work is finished by P and Q in 7 hours.
Therefore, P and Q completed 2/3rd of the work in 7 hours.
This implies P and Q together can complete the work in 21/2 hours.
Let the total work be LCM(6, 21/2), i.e. 42 units.
P, Q and R together can complete 7 units in one hour.
P and Q together can complete 4 units in one hour.
This implies, R can complete 3 units in one hour.
Time taken by R alone to complete the work = $$\frac{42}{3}$$ = 14 hours
The answer is option C.
One pipe can fill a tank three times as fast as another pipe. If the two pipes together can fill the tank in 36 minutes, then the slower pipe will take how much time to fill the tank alone?
Let slower pipe fill the tank at the rate x units/ minute.
Faster pipe will fill tank at the rate of 3x units/ minute
Number of units filled by both the pipes in a minute = 4x
Total time taken to fill tank = 36 minutes
capacity of tank = 36$$\times\ $$4x = 144x
Time taken by slower pipe to fill the tank = $$\frac{144x}{x}$$ = 144 minutes
Answer is option D.
Given: Anuj takes 1 day to complete a job. Bharat takes twice the time as Anuj to complete the same job. Chetan takes twice the time as Bharat to complete that job. Dhiraj takes twice the time as Chetan to complete that job.
(A) Chetan and Dhiraj will take 8/3 days to complete the work
(B) The second fastest pair to complete the work is Anuj and Dhiraj
(C) The second slowest pair to complete the work is Bharat and Dhiraj
(D) Bharat and Dhiraj will take 4/3 days to complete the work
Anuj takes 1 day to complete
Bharat takes 2 days
Chetan takes 4 days and Dhiraj takes 8 days to complete
option A chetan and Dhiraj together will take $$\frac{4\times\ 8}{4+8}=\frac{32}{12}=\frac{8}{3\ }days$$so A is correct.
Now calculating for all we get AB in 2/3 days AC in 4/5 days AD in 8/9 days BC in 8/6 days BD in 16/10 days
So we can say BD is 2nd slowest pair
Hence A and C are correct
Two pipes A and B can fill a tank in 5 hours and 20 hours respectively. Both pipes together can fill the same tank in:
Let the volume be 20 units
So A fills at 4 units/hr
B fills at 1 unit/hr
Now together they fill 4+1 = 5 units/ hour
Now time taken to fill completely : 20/5 = 4 hrs
L and M together can complete a piece of work in 72 days, M and N together can complete it in 120 days, and L and N together in 90 days. In what time can L alone complete the work?
Let L does a units of work/day
M does b units of work/ day
N does c units of work/ day
Now as per given conditions :
Let work be W
So we get
W = 72(a+b) =120(b+c) =90(a+c)
we get
6a+6b = 10b +10c
we get 6a-4b-10c=0 (1)
also
4a+4b =5a+5c
we get a-4b+5c =0 (2)
From (1) and (2)
we get a=3 , b=2 and c=1
Now therefore W = 360
Now time taken by L alone to complete the work = 360/3 = 120 days
The work done by a man, woman and child are in the ratio 3: 2:1. If daily wages of 20 men, 30 women and 36 children amount to 78/-, what will be the wages of 15 men, 21 women and 30 children for 18 weeks ?
Let the efficiency of a man, woman and child be $$3x,2x,x$$ espectively.
Thus, 1 day wage = $$(3x\times20)+(2x\times30)+(x\times36)=78$$
=> $$156x=78$$
=> $$x=\frac{1}{2}$$
$$\therefore$$ Wages of 15 men, 21 women and 30 children for 18 weeks = $$[(15\times3x)+(21\times2x)+(30\times x)]\times18\times7$$
= $$117\times\frac{1}{2}\times126$$
= $$117\times63=Rs.$$ $$7,371$$
=> Ans - (A)
A city has an average demand of water of 33,000 Lts. of water which lasts for 50 days. But if some people enter the city, then the demand increases to 37,000 Lts. of water for which supply will lasts 35 days. Give an estimation of how much minimum water should be used daily so that it could last 50 days ?
Water capacity for 50 days is
33000 x 50= 1650000.-----------(1)
water capacity for 35 days is
37000 x 35= 1295000------------(2)
Let the minimum water to be used is K litres
so, K x15=355000
K=$$\ \frac{355000\ }{15}$$
K= 23666.66litres.
Therefore, estimation of how much minimum water should be used daily so that it could last 50 days is 23666.66liters.
Rajesh can check the quality of 1000 items in 5 hours and Rakesh can complete 75% of the same job in 3 hours. How much time is required for both of them to check 1300 items, if Rakesh stops checking after 2 hours ?
Given, Rajesh can check the quality of 1000 items in 5 hours
$$\Rightarrow$$ Efficiency of Rajesh = 200 items/hr.
Also given, Rakesh can complete the 75% of same job in 3 hours
$$\Rightarrow$$ time taken by Rakesh to complete 100% of the job = $$\frac{100}{75}\times 3$$ = 4 hours.
$$\Rightarrow$$ Efficiency of Rakesh = 250 items/hr.
Given in the process of checking 1300 items, Rakesh spends only 2 hours. Let say time spent by Rajesh be 't' hours, which is also the total time taken.
Total Work = Efficiency $$\times$$ time taken
$$\Rightarrow 1300 = 250\times 2 + 200\times t$$
$$\Rightarrow 200t = 800$$
$$\Rightarrow t = 4$$
Hence the time taken in the process of checking 1300 items is 4 hours.
Two pipes A and B can fill a cistern in 120 minutes and 150 minutes respectively. There is also an outlet C.If all the three pipes are opened together, the cistern gets filled in 100 minutes. How much time will be taken by C to empty full tank?
Let the capacity of the cistern be 600 units.
From the given data, the efficiencies of pipes A and B are 5 units/ min and 4 units/min respectively.
Let the efficiency of outlet pipe C be 'k' units/min.
Given the time taken to fill the cistern when all the three pipes are open = 100 minutes
$$\Rightarrow Efficiency of pipes\times time taken = Capacity of cistern$$.
$$\Rightarrow (5+4-k)\times 100 = 600$$
$$\Rightarrow 9-k = 6$$
$$\Rightarrow k = 3$$
Therefore the time taken(t) by pipe C to empty the cistern = $$Capacity of the cistern\div efficiency of pipe C$$
$$\Rightarrow t = 600\div 3 = 200 minutes = 3 hrs 20 min$$.
Ramesh works A hours a day and rests B hours a day. This pattern continues for 1 week, with an exactly opposite pattern next week, and so on for four weeks. Every fifth week he adopts a new pattern which then continues for the next four weeks. When he works longer than he rests, his wage per hour is three times what he earns per hour when he rests longer than he works. The following table shows his daily working hours for the week numbered 1 to 13.
A week consists of six days and a month consists of four weeks. If Ramesh is paid Rs. 60 per working hour in
the $$1^{st}$$ week, what is his salary for the $$1^{st}$$ month? (Assume that he is paid half his wages for his resting hours on duty)
As per the given conditions, weeks 1 and 3 will have similar pay structure and weeks 2 and 4 will have similar pay structure.
For weeks 1 and 3
wage/hr for working = 60
wage/hr during rest = 30
Total payment per day = (60*6 )+ (30*3) = 450
Total payment for weeks 1 and 3 = 450 * 12 = 5400
For weeks 2 and 4
wage/hr for working = 20
wage/hr during rest = 10
Total payment per day = (20*3 )+ (10*6) = 120
Total payment for weeks 2 and 4 = 120 * 12 = 1440
$$\therefore $$ Total monthly salary = 5400 + 1440 = 6840
Hence, option A.
If 26 horses or 20 bullocks eat up the fodder in store in 170 days, in what time will 10 horses and 8 bullocks finish the same quantity of fodder?
Let amount eaten by each horse and each bullock in one day be 'h' units and 'b' units respectively.
So Total fodder = Total effciency$$\times$$Total number of days
$$\Rightarrow$$ Total work = 26$$\times$$h$$\times$$170 = 20$$\times$$b$$\times$$170
$$\Rightarrow$$ b = 1.3h............(1)
The amount of fodder eaten by 10 horses and 8 bullocks in one day = 10h + 8b = 10h + 8(1.3h) = 20.4h
Time taken by them to eat the same amount of fodder = total fodder/amount eaten by them in one day
= $$\frac{ 26\times h\times 170}{20.4h}$$
= 216.67 days
Anil is twice as good a student as Bharat and is able to finish a work in 30 minutes less than Bharat’s time. Find the time in which both of them can finish the same work together?
Given Anil is twice as good a student as Bharat
$$\Rightarrow$$ Efficiency of Anil : Efficiency of Bharat = 2:1
and also, Efficiency is inversely proportional to Time taken,
$$\Rightarrow$$ Time taken by Anil : Time taken by Bharat = 1:2...............................(1)
Given that Time taken by Anil is 30 min less than Bharat's time.
Let say, Time taken by Bharat be 't' minutes.
Then the time taken by Anil = t-30 minutes
Substituting these in equation (1), we get
$$\frac{t-30}{t} = \frac{1}{2}$$
$$\Rightarrow$$ t = 60 minutes.
Therefore the time taken by Anil and Bharat are 30 minutes and 60 minutes respectively.
Let Efficiency of Bharat be 'x', then Efficiency of Anil will be '2x'
$$\Rightarrow$$ Total Work = Efficiency\times Time taken = $$(2x)\times 30 (or) (x)\times 60 = 60x$$ units.
Efficiency when Anil and Bharat are working together = x+2x = 3x
Total Work = 60x units
Time taken(T) by Anil and Bharat together to complete the work = Total work/ Efficiency when Anil and Bharat work together
$$\Rightarrow T = \frac{60x}{3x}$$
$$\Rightarrow$$ T = 20 minutes.
Working together, Rakesh, Prakash and Ashok can finish the same job in an hour. Also, if Prakash works for an hour, and then Ashok works for four hours, the job will be completed. If Rakesh can do the job an hour quicker than Prakash, how many hours would Ashok take to complete the job alone?
Let the efficiencies of Rakesh, Prakash, and Ashok be 'r' 'p' and 'a' respectively.
GIven that Rakesh can do a job an hour quicker than Prakash.
So let time taken by Prakash be 't' hours, then time taken by Rakesh will be 't-1' hours.
Total work(W) = Efficiency$$\times$$ Time taken = p$$\times$$ t = r$$\times$$ (t-1)
$$\Rightarrow$$ t = $$\frac{r}{r-p}$$....................(1)
Given that, Working together, Rakesh, Prakash and Ashok can finish the same job in an hour.
$$\Rightarrow$$ Total work(W) = (r+p+a) (1) units.............(2)
Also given that, if Prakash works for an hour, and then Ashok works for four hours, the job will be completed.
$$\Rightarrow$$ Total work(W) = p(1) + a(4) units...........(3)
Equating (2) and (3), we get
(r+p+a) (1) = p(1) + a(4)
$$\Rightarrow$$ r = 3a..............(4)
Substituting this value in equation (1), we get
t = $$\frac{3a}{3a-p}$$.............(5)
As the Total work is always constant, p$$\times$$ t = p(1) + a(4)
$$\Rightarrow$$ t = 1 + 4$$\frac{a}{p}$$.......(6)
Equating (5) and (6), we get
$$\frac{3a}{3a-p} = 1 + 4\frac{a}{p}$$
Let $$\frac{a}{p}$$ = 'k'
$$\Rightarrow \frac{3k}{3k-1} = 1 + 4k$$
$$\Rightarrow 3k = 12k^2 + 3k - 4k -1$$
$$\Rightarrow 12k^2 - 4k - 1 = 0$$
Solving for k, we get k = $$\frac{1}{2} or -\frac{1}{6}$$[which is not possible]
Hence k = $$\frac{1}{2}$$
$$\Rightarrow$$ p =2a.............(7)
Substituting (4) and (7) in equation (2) we get,
Total work(W) = 6a units.
Time taken by Ashok alone to do the job = Total work/ Efficiency of Ashok
= 6a/a
=6 hours.