Question 63

F alone can complete a work in 24 days and G alone can complete the same work in 32 days. F and G start the work together but G leaves the work 8 days before the completion of work. In how many days the total work will be completed?

Solution

Let total work to be done = L.C.M.(24,32) = 96 units

=> F's efficiency = $$\frac{96}{24}=4$$ units/day and G's efficiency = $$3$$ units/day

Let the work is finished in $$t$$ days, then F alone worked for 8 days, and F and G together worked for $$(t-8)$$ days

According to ques,

=> $$7(t-8)+(4\times8)=96$$

=> $$7t-56+32=96$$

=> $$t=\frac{120}{7}$$ days

=> Ans - (D)


Create a FREE account and get:

  • Free SSC Study Material - 18000 Questions
  • 230+ SSC previous papers with solutions PDF
  • 100+ SSC Online Tests for Free

cracku

Boost your Prep!

Download App