Instructions

The following table refers to hotel construction projects. The cost of project increased at the rate of 10% per annum; if completed beyond 1997.

Question 115

What is the cost incurred for projects completed in 1999?

Solution

Cost incurred for projects completed in 1999

= $$(275+235+250+300)\times(1.1)^2=Rs.$$ $$1282.6$$ crore

=> Ans - (B)


Create a FREE account and get:

  • All Quant Formulas and Shortcuts PDF
  • 100+ previous papers with solutions PDF
  • Top 5000+ MBA exam Solved Questions for Free

cracku

Boost your Prep!

Download App