The following table refers to hotel construction projects. The cost of project increased at the rate of 10% per annum; if completed beyond 1997.

Question 115

What is the cost incurred for projects completed in 1999?

Solution

Cost incurred for projects completed in 1999

= $$(275+235+250+300)\times(1.1)^2=Rs.$$ $$1282.6$$ crore

=> Ans - (B)