The following table refers to hotel construction projects. The cost of project increased at the rate of 10% per annum; if completed beyond 1997.
Cost incurred for projects completed in 1998
= $$(250+225)\times(1.1)=Rs.$$ $$522.5$$ crore
=> Ans - (C)