The following table refers to hotel construction projects. The cost of project increased at the rate of 10% per annum; if completed beyond 1997.

Question 114

What is the cost incurred for projects completed in 1998?

Solution

Cost incurred for projects completed in 1998

= $$(250+225)\times(1.1)=Rs.$$ $$522.5$$ crore

=> Ans - (C)