Instructions

The following table refers to hotel construction projects. The cost of project increased at the rate of 10% per annum; if completed beyond 1997.

Question 114

What is the cost incurred for projects completed in 1998?

Cost incurred for projects completed in 1998

= $$(250+225)\times(1.1)=Rs.$$ $$522.5$$ crore

=> Ans - (C)

Create a FREE account and get:

  • All Quant Formulas and Shortcuts PDF
  • 100+ previous papers with solutions PDF
  • Top 5000+ MBA exam Solved Questions for Free

MAT Quant Questions | MAT Quantitative Ability

MAT DILR Questions | LRDI Questions For MAT

MAT Verbal Ability Questions | VARC Questions For MAT