The following table refers to hotel construction projects. The cost of project increased at the rate of 10% per annum; if completed beyond 1997.
For projects completed in 2000, cost = Rs. 250 crore
Total cost (with tax) = $$250\times (1.1)^3=Rs.$$ $$332.75$$ crore
Total costs of projects completed in 1998 = $$(250+225)\times(1.1)=Rs.$$ $$522.5$$ crore
Total costs of projects completed in 1999 = $$(275+235+250+300)\times(1.1)^2=Rs.$$ $$1282.6$$ crore
$$\therefore$$ Total cost = $$332.75+522.5+1282.6\approx2140$$ crore
=> Ans - (A)