Question 100

A person A can turnout thrice as much work as B can do. B alone can complete that work in 20 days. After both of them worked together for 4 days, A left the work and B continued till the end. Then the time (in days) taken by B to complete the remaining work after A left the job, is

Solution

Let the total work be 60 units. 
Hence, capacity of B = 3 units/day and thus, capacity of A = 9 units/day
A and B work together for 4 days, hence, work completed = 48 units
Remaining work = 12 units completed by B in 12/3 = 4 days


Create a FREE account and get:

  • Download Maths Shortcuts PDF
  • Get 300+ previous papers with solutions PDF
  • 500+ Online Tests for Free

cracku

Boost your Prep!

Download App