For the following questions answer them individually
Which of the following estimate is carried out if the sectioned estimate exceeds 5% due to the change in the price?
For estimation of the masonry work and excavation work, accuracy requirement in the measurement of the length as compared to thickness or width is _____.
A wall of width 300 mm contains two T junctions. The height of the wall is 3 m and total length of the central line is 150 m. Calculate the quantity of the brick work (in cubic meter) using central line method.
For estimation of the brick masonry, no deduction is made for the end of the rafter up to the area (square inch) of
Calculate the quantity (cubic meter) of the concrete used in a pier of 1.2 m diameter and 6 m length. The pier is reinforced with 8 bars of 25 mm diameter.
In long wall and short wall method, the length of the short wall is the equal to the center to center length of wall minus _____.
Calculate the quantity (cubic meter) of the earthwork for a canal of 50 m long. Depths of canal at two extreme sections are 3 m and 5 m. The bottom width and top width of the canal are 2 m and 4 m. Use midsection method.
Calculate the value of a pump after 5 years, if the annual depreciation value is Rs. 200. The original cost of the pump is Rs. 3000 and the useful life of the pump is 10 years.
Which of the following is NOT included in the floor area?
1) Clear coverage area
2) Area of the walls
3) Sills of the doors
4) Sills of the windows