Manoj can do a piece of work in 42 hours. If he is joined by Jayashree who is 100% more efficient, in what time they will finish the work together?
Let total work to be done = 42 units
Manoj's efficiency = $$\frac{42}{42} = 1$$ unit/hr
Jayashree is 100% more efficient, => Jayashree's efficiency = $$1 + \frac{100}{100} \times 1 = 2$$ units/hr
(Manoj + Jayashree)'s 1 day's work together = 1 + 2 = 3 units/hr
$$\therefore$$ Time taken by Manoj and Jayashree together to finish the work = $$\frac{42}{3} = 14$$ hours
=> Ans - (C)