P and Q can do a project in 12 and 12 days respectively. In how many days can they complete 50% of the project if they work together?
Let total work to be done = 12 units
P can complete the work alone in 12 days
=> P's efficiency = $$\frac{12}{12} = 1$$ unit/day
Q can complete the work alone in 12 days
=> Q's efficiency = $$\frac{12}{12} = 1$$ unit/day
(P + Q)'s 1 day's work = 1 + 1 = 2 units/day
=> 50% of the work = $$\frac{50}{100} \times 12 = 6$$ units
$$\therefore$$ Time taken by them together to complete 50% of the work = $$\frac{6}{2} = 3$$ days
=> Ans - (B)