P is twice as good a workman as Q and together they finish a piece of work in 20 days. In how many days will P alone finish the work ?
Let Q's efficiency = $$x$$ units/day
=> P's efficiency = $$2x$$ units/day
Together they finish the work in 20 days.
=> Total work = $$20\times(x+2x)=20\times3x=60x$$ units
$$\therefore$$Â Days taken by P alone to finish the work = $$\frac{60x}{2x}=30$$ days
=> Ans - (A)