A and B can complete a workin 20 days .B and C can complete the same work in 24 days.The work was started by A and he work for 8 days,then after B wors for 11 days and the C completes the remaining work in 22 days,then the number of days required for c alone to complete the work is
Let the total work be 120 units and let the per day capacities of A,B,C be a, b, c units
Hence,
a + b = 6 ..... (A)
b + c = 5 ..... (B)
Hence, a + 2b + c = 11 ..... (C) & a - c = 1 ..... (D)
Also, given that:
8a + 11b + 22c = 120 ..... (E)
Multiplying (A) by 6 and (B) by 5, adding both, we get 6a + 11b + 5c = 61 ..... (F)
Subtracting (F) from (E), we get: 2a + 17c = 59 ..... (G)
Multiplying (D) by 2, subtracting from (G), we get
19c = 57
c = 3
Hence, C alone takes 120/3 = 40 days to complete work
Create a FREE account and get:
Book Free CAT Mentorship
Get personalized CAT strategy from a 99%iler
500+ students mentored
OTP Verification
Enter the 6-digit code sent to your phone
Booking Summary
Enter OTP
Didn't receive the OTP?
Start your IIM journey with the right preparation and crack CAT 2026.
Educational materials for CAT preparation