A and B can complete a piece of work in 15 days and 10 days respectively. They got a contract to complete the work for ₹75000. The share of B (in ₹) in the contracted money will be:
Let the total work be $$T$$
Work done by A in 1 day = $$\frac{\ T}{15}$$
Work done by B in 1 day = $$\frac{\ T}{10}$$
Ratio of their shares = $$\frac{\ T}{15}:\frac{\ T}{10}$$ $$= 10 : 15 = 2 : 3$$
Share of B $$=\frac{ 3}{5}\times75000 =45000$$