P and Q can do a project in 25 and 50 days respectively. In how many days can they complete 18% of the project if they work together?
Let total work to be done = 50 units
P can complete the work alone in 25 days
=> P's efficiency = $$\frac{50}{25} = 2$$ units/day
Q can complete the work alone in 50 days
=> Q's efficiency = $$\frac{50}{50} = 1$$ unit/day
(P + Q)'s 1 day's work = 2 + 1 = 3 units/day
=> 18% of the work = $$\frac{18}{100} \times 50 = 9$$ units
$$\therefore$$ Time taken by them together to complete 18% of the work = $$\frac{9}{3} = 3$$ days
=> Ans - (B)