A can built up a structure in 8 days and B can break it in 3 days. A has worked for 4 days and then B joined to work with A for another 2 days only. In how many days will A alone build up the remaining part of the structure?
Let the total work be 24 units
So we can say work done by A will be +3 units / day
and work done by B will be -8 units/day
Now as per the given condition :
work done by A in 4 days = 3(4) 12 units
Now, both worked for 2 days:
so work done will be (3-8)(2) = -10 units
Now the net work will be 12-10 = 2 units
Now remaining work 24-2 =22 units
Therefore A will complete this in 22/3 = $$7\frac{1}{3}$$ days
Was this solution helpful?
Create a FREE account and get:
Book Free CAT Mentorship
Get personalized CAT strategy from a 99%iler
500+ students mentored
OTP Verification
Enter the 6-digit code sent to your phone
Booking Summary
Enter OTP
Didn't receive the OTP?
Start your IIM journey with the right preparation and crack CAT 2026.
Educational materials for CAT preparation