SNAP Time and Work Questions

SNAP 2018 Time and Work questions

Question 1

A is able to do a piece of work in 10 days and B can do the same work in 15 days. If they can work together for four days, what is the fraction of work left?

Show Answer Explanation

SNAP 2015 Time and Work questions

Question 1

A, B and C can do a work in 6, 8 and 12 days respectively. If they do the work together and earn Rs. 2700, what is the share of C in that amount ?


Question 2

Three pipes A, B and C can fill a tank in 12 hours. All the pipes started working together and after 3 hours, C is closed. If A and B can fill the remaining part in 10 hours, then the number of hours taken by C alone to fill the tank is .

Show Answer Explanation

SNAP 2014 Time and Work questions

Question 1

A can do a piece of work in 25 days and B in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?

SNAP 2013 Time and Work questions

Question 1

A and B together can complete a task in 20 days. B and C together can complete the same task in 30 days. A and C together can complete the same task in 40 days. What is the respective ratio of the number of days taken by A when completing the same task alone to the number of days taken by C when completing the same task alone ?


Question 2

A certain number of people were supposed to complete a work in 24 days. The work, however, took 32 days, since 9 people were absent throughout. How many people were supposed to be working originally?

Show Answer Explanation

Question 3

A pump can be operated both for filling a tank and for emptying it. The capacity of tank is 2400 $$m^3$$ .The emptying capacity of the pump is 10 $$m^3$$ per min higher than its filling capacity. Consequently, the pump needs 8 min less to empty the tank than to fill it. Find the filling capacity of the pump.

Show Answer Explanation

Question 4

8 men and 4 women together can complete a piece of work in 6 days. The work done by a man in one day is double the work done by a woman in one day. If 8 men and 4 women started working and after 2 days 4 men left and 4 new women joined, in how many more days will the work be completed?

SNAP 2011 Time and Work questions

Question 1

B is twice efficient as A and A can do a piece of work in 15 days. A started the work and after a few days B joined him. They completed the work in 11 days, from the starting. For how many days did they work together?


Question 2

Four men and three women can do a job in 6 days. When 5 men and 6 women work on the same job, the work gets completed in 4 days. How long will 2 women and 3 men take to do the job?

Show Answer Explanation

Question 3

Ram completes 60% of a task in 15 days and then takes the help of Rahim and Rachel. Rahim is 50% as efficient as Ram is and Rachel is 50% as efficient as Rahim is. In how many more days will they complete the work?

Show Answer Explanation

Question 4

A and B can do a piece of work in 21 and 24 days respectively. They start the work together and after some days A leaves the work and B completes the remaining work in 9 days. After how many days did A leave?


Question 5

Amit can do a work in 12 days and Sagar in 15 days. If they work on it together for 4 days, then the fraction of the work that is left is:

SNAP 2010 Time and Work questions

Question 1

Running at the same constant rate, 6 identical machines can produce a total of 180 bottles per hour. How many bottles could 15 such machines produce in 30 minutes?

Show Answer Explanation

Question 2

It takes 6 hours for pump A, used alone, to fill a tank of water. Pump B alone takes 8 hours to fill the same tank. A, B and another pump C all together fill the tank in 2 hours. How long would pump C take, used alone, to fill the tank?

Show Answer Explanation

Question 3

A swimming pool can be filled by pipe A in 3 hours and by pipe B in 6 hours, each pump working on its own. At 9 am, pump A is started. At what time will the swimming pool be filled if pump B is started at 10 am?

Show Answer Explanation

Question 4

Stuart, Jack and Leo are colleagues working in a plant. Stuart and Jack can do a work in 10 days, Jack and Leo can do the same work in 15 days while Stuart and Leo can do it in 12 days. All of them started the work together. After two days, Leo was shifted to some other work. How many days will Stuart and Jack take to finish the rest of the work?

Show Answer Explanation

SNAP 2009 Time and Work questions

Question 1

A contract is to be completed in 50 days and 105 men were set to work, each working 8 hours a day. After 25 days, $$\frac{2}{5}th$$ of the work is finished. How many additional men be employed so that the work may be completed on time, each man now working 9 hours a day?

Show Answer Explanation

Question 2

A can built up a structure in 8 days and B can break it in 3 days. A has worked for 4 days and then B joined to work with A for another 2 days only. In how many days will A alone build up the remaining part of the structure?

Show Answer Explanation

SNAP 2006 Time and Work questions

Question 1

If 5 spiders can catch five flies in five minutes. How many flies can hundred spiders catch in 100 minutes?

Show Answer Explanation
cracku

Boost your Prep!

Download App