Question 27

A contract is to be completed in 50 days and 105 men were set to work, each working 8 hours a day. After 25 days, $$\frac{2}{5}th$$ of the work is finished. How many additional men be employed so that the work may be completed on time, each man now working 9 hours a day?

Solution

It is given that in the initial 25 days, the work done by 105 men was $$(2/5)^{th}$$ of the total work.
Thus, the total work left is $$(3/5)^{th}$$ of the total work.
MDH/W is constant 
so we get 
$$\frac{105\times\ 25\times\ 8}{\frac{2W}{5}}=\frac{M\times\ 25\times\ 9}{\frac{3W}{5}}$$
We get M =140
So additional men = 140-105 = 35


Create a FREE account and get:

  • All Quant Formulas and shortcuts PDF
  • 40+ previous papers with solutions PDF
  • Top 500 MBA exam Solved Questions for Free

cracku

Boost your Prep!

Download App