Question 15

30 women do half of the total work in 30 days. How many more women will be required to complete the remaining work in 10 days?

Solution

30 women do half of the total work in 30 days

Let $$x$$ women are required to complete the remaining half work.

Using, $$M_1D_1=M_2D_2$$

=> $$30\times30=x\times10$$

=> $$x=\frac{900}{10}=90$$

$$\therefore$$ Number of more women required = $$90-30=60$$

=> Ans - (C)