In an office, 75 employees can finish a project in 60 days. After few days, 15 employees left the job and the project was completed in 65 days. After how many days did the 15 employees leave?
50
45
30
40
Create a FREE account and get:
SSC Data Interpretation
SSC Geometry
SSC Linear Equations
SSC Number Systems
SSC Quadratic Equations
SSC Trigonometry
SSC Ages
SSC Arithmetic
SSC Reading Comprehension
SSC Vocabulary
SSC Analogy
SSC Coding Decoding
SSC Directions
SSC Meaningful Order
SSC Number Series
SSC Puzzles
SSC Syllogisms
SSC Words Formation
SSC Venn Diagram
Login to your Cracku account.
Enter Valid Email
Follow us on
Incase of any issue contact support@cracku.in
Boost your Prep!
Quick, Easy and Effective Revision
By proceeding you agree to create your account
Free CAT Formulae PDF will be sent to your email address soon !!!