Time and cost over-runs have been a major problem affecting the implementation of Central Sector Projects. The trend of time over-runs and cost over-runs are given in the graphs below. Answer these questions based on these graphs.


The highest incidents of cost over-run during the given period has been in the year
Cost over-run during the year
1991 = 61.6% [MAX]
1994 = 57.5%
1997 = 45%
=> Ans - (A)