Time and cost over-runs have been a major problem affecting the implementation of Central Sector Projects. The trend of time over-runs and cost over-runs are given in the graphs below. Answer these questions based on these graphs.

Question 109

The number of delayed projects have been the samein the years

Solution

Number of delayed projects in the years :

(A) : 1990 and 1992 are 194 each

(B) : 1989 and 2001 are 174 each

Thus, projects delayed are same in both set of years.

=> Ans - (C)