Time and cost over-runs have been a major problem affecting the implementation of Central Sector Projects. The trend of time over-runs and cost over-runs are given in the graphs below. Answer these questions based on these graphs.


Number of delayed projects in the years :
(A) : 1990 and 1992 are 194 each
(B) : 1989 and 2001 are 174 each
Thus, projects delayed are same in both set of years.
=> Ans - (C)