Time and cost over-runs have been a major problem affecting the implementation of Central Sector Projects. The trend of time over-runs and cost over-runs are given in the graphs below. Answer these questions based on these graphs.
The percentage cost over-runs have been the samein the years 2000 and 2001. It implies that
The percentage cost over-runs have been the same in the years 2000 and 2001, i.e. 36%. It simply implies that the cost over-runs have been the same for both years.
=> Ans - (A)