Time and cost over-runs have been a major problem affecting the implementation of Central Sector Projects. The trend of time over-runs and cost over-runs are given in the graphs below. Answer these questions based on these graphs.

Question 107

The highest numberof delayed projects during the given period wasin the year

Number of delayed projects during the years :

(A) : 1991 = 189

(B) : 1994 = 210

(C) : 1997 = 239     [MAX]

(D) : 1996 = 234

=> Ans - (C)