The following table refers to hotel construction projects. The cost of the project increased at the rate of 10% per annum; if completed beyond 1997.
Lokhandwala Group: 225/536 = 0.42
Raheja Group: 250/500 = 0.5
IHCL: 275/600 = 0.458
ITC: 300/300 = 1
So, the required answer is Lokhandwala Group.