Question 75

Four men and three women can do a job in 6 days. When 5 men and 6 women work on the same job, the work gets completed in 4 days. How long will 2 women and 3 men take to do the job?

(4M+ 3W)6 = (5M+6W)4 = W

4M = 6W

2M = 3W

let x be the number of days taken by 2 women and 3 men take to do the job

(4M+3W)6=(2W+3M)x

9W*6=6.5W*x

x=8.3 days

C is the correct answer.