Question 74

A can do a certain job in 12 days. B is 60% more efficient than A. To do the same job B alone would take?

Solution

Let the total work be 60 days.
Efficiency of A = 60/12 = 5 units per day
Efficiency of B = 160% of Efficiency of A = 160% of 5 = 8 units per day
Therefore, B can do the work in $$\dfrac{60}{8} = 7\dfrac{1}{2}$$ days


Create a FREE account and get:

  • Free SSC Study Material - 18000 Questions
  • 230+ SSC previous papers with solutions PDF
  • 100+ SSC Online Tests for Free

cracku

Boost your Prep!

Download App