A work can be completed by 35 workers in 30 days. If 5 workers leave after every 10 days then in how many days will the work be completed?
$$M_1\times D_1\ =\ M_2\times D_2$$
Let's assume the more number of days taken after 30 days is 'y'.
$$35\times30\ =\ 35\times10+30\times10+25\times10+20\times y$$
$$1050\ =\ 350+300+250+20y$$
20y+900 =Â 1050
20y =Â 1050-900
20y = 150
y = 7.5
So the total number of days taken = 30+7.5 =Â 37.5 days