Sign in
Please select an account to continue using cracku.in
↓ →
A can complete a work in 18 days, while B can complete it in 12 days. B worked on it for 4 days. How long will A take to finish the remaining work?
Create a FREE account and get:
Start your IIM journey with the right preparation and crack CAT 2026.
Educational materials for CAT preparation