A work can be completed by X men in 15 days. 10 more men join them after 3 days. The remaining work is now completed in 8 days. What is the value of X?
$$men_1\times\ days_1\ =\ men_2\times\ days_2$$
$$X\times\ 15\ =\ X\times\ 3+\left(X+10\right)\times8$$
$$15X\ =\ 3X+8X+80$$
$$15X\ =\ 11X+80$$Create a FREE account and get: