A can finish a piece of work in 48 days and B can finish it in 60 days. They work together for 12 days and then A goes away. In how much time (in days and hours) will B finish 25% of the remaining work?
6 days 4 hours
8 days 8 hours
6 days 6 hours
8 days 6 hours