P can do a piece of the work in 18 days and Q can do same work in 36 days. How long will they take (in days), if they work together, to complete the above mentioned work?
24
12
20
10
Create a FREE account and get:
Time Speed Distance
Coordinate Geometry
Averages, Ratio and Proportion
Linear Equations
Mensuration
Averages
Profit, Loss and Interest
Arithmetic
Averages Mixtures Alligations
Geometry
Number Systems
Time And Work
Probability, Combinatorics
Inequalities
Logarithms
Progressions and Series
Quadratic Equations
Data Sufficiency
Time, Distance and Work
Percentages
Remainders
Logarithms, Surds and Indices
Number Series
Venn Diagrams
Algebra
Profit And Loss
Simple Interest Compound Interest
Functions, Graphs and Statistics
Login to your Cracku account.
Follow us on
Incase of any issue contact support@cracku.in
Boost your Prep!