P and Q can do a project in 60 and 30 days respectively. In how many days can they complete 90% of the project if they work together?Â
Let total work to be done = 60 units
P can complete the work alone in 60 days
=> P's efficiency = $$\frac{60}{60} = 1$$ unit/day
Q can complete the work alone in 30 days
=> Q's efficiency = $$\frac{60}{30} = 2$$ units/day
(P + Q)'s 1 day's work = 1 + 2 = 3 units/day
=> 90% of the work = $$\frac{90}{100} \times 60 = 54$$ units
$$\therefore$$ Time taken by them together to complete 90% of the work = $${54}{3} = 18$$ days
=> Ans - (D)